HOME | WHAT IS HYDRO | BENEFITS OF HYDRO | ROLE OF RENEWABLES | WYRE WYND | DAYVILLE POND | COLLINSVILLE | PHOTOS | CONTACT

Wyre Wynd Hydro
Jewett City, Connecticut

The Wyre Wynd facility was originally built Circa 1913 and retired in 1955 after sustaining flood damage. In 1983 the Wyre Wynd Company built a new powerhouse and installed new equipment. In 1997 SHI bought the site and since that date has performed major improvements, repairs and upgrades which have made the project more reliable, more efficient, more environmentally friendly, and easier to operate.

This work included installation of tailgate gantry system, replacement of blade seals with improved design, upgrade of Allen Bradley PLC, rewriting PLC program for more efficient operation, switchgear re-design, replacement of switchgear relays, installation of additional protective devices, installation of trash rake system, flashboard replacement, dewatering pump installation, design and installation of trash conveyor system and replacement of trash racks.

Current ongoing work at the site includes installation of indoor and outdoor cameras, fisheries protection devices, new CAD drawings and automation of trash rake.

Recent major maintenance involved the replacement of the stub shaft. The project was taken off line to do normal maintenance of replacing upstream seals and bearing. Removal of the bearing housing exposed the stub shaft which has not been visible since the last time the seals and bearing were replaced in 1996. Immediately evident were deep visible cracks in the radius area of the shaft. This required the relatively large job of replacing the stub shaft. The stub shaft replacement job was performed by Summit Hydropower and Lee Mechanical, Inc. Regarding the method of manufacturing the new shaft Summit decided to install a forged rather than a welded shaft (the original shaft was a weldment) due to the superior strength of a forging. The job was completed and the project put back on line 2/8/14. Cost was about $200,000. While the project was off line Summit performed several improvements including draft tube blast and epoxy coat, replace wicket gate bearings and seals, replacing quad seals and update the project computer program. In many respects the project has been improved such that it is of higher quality and more reliable than when it was originally built in 1984.

Wyre Wynd consists of two generating units: An Allis Chalmers double regulated 138.5 RPM Kaplan turbine directly connected to a 2,700 kW Siemens synchronous generator plus an Allis Chalmers 514 RPM propeller turbine belt connected to an 80 kW 900 RPM induction generator. Wyre Wynd has a total installed capacity of 2,780 kW and produces an average of 10,100,000 kWh of electricity per year, enough for about 2,000 households and enough to avoid the importation and burning of about 17,000 barrels of oil per year.

Photos of Wyre Wynd Site
Click on any photo to zoom

 
Click photo to enlarge,
use back button to return to page

Adam installing hub after rehabilitation

Return to Top


Click photo to enlarge,
use back button to return to page

New turbine bearing and half of oil sump installed.

Return to Top


Click photo to enlarge,
use back button to return to page

Original stub shaft that was replaced due to cracks visible in radius area. Flange diameter = 4'.

Return to Top


Click photo to enlarge,
use back button to return to page

Water fairing was cut and modified to make it detachable so that hub could be moved upstream six additional inches to allow hub removal

Return to Top


Click photo to enlarge,
use back button to return to page

Draft tube and shaft looking upstream after sand blast and 4 coats of Belzona immersion epoxy

Return to Top


Click photo to enlarge,
use back button to return to page

Gary Lee of Lee Mechanical, Inc. making adjustments during spherical bearing install.

Return to Top


Click photo to enlarge,
use back button to return to page

Donny applying torque to shaft bolts

Return to Top


Click photo to enlarge,
use back button to return to page

Donny and Adam installing seal carrier

Return to Top


Click photo to enlarge,
use back button to return to page

Bob and Chris working on wicket gates. Think of them as a radial Venetian blind. They control water flow to the turbine.

Return to Top


Click photo to enlarge,
use back button to return to page

Refurbished seal carrier with new seals

Return to Top


Click photo to enlarge,
use back button to return to page

Runner hub after refurbishment with new stub shaft

Return to Top


Click photo to enlarge,
use back button to return to page

Bearing/seal carrier housing showing new stainless drain piping

Return to Top


Click photo to enlarge,
use back button to return to page

Duncan installing a (voluntary) fish protection device in draft tube

Return to Top


Click photo to enlarge,
use back button to return to page

View of runner hub before removal for stub shaft replacement job, October 2013.

Return to Top


Click photo to enlarge,
use back button to return to page

Runner hub and cracked stub shaft being removed

Return to Top


Click photo to enlarge,
use back button to return to page

Runner being hoisted out of powerhouse. End of stub shaft shows the blade operating shaft which moves longitudinally to adjust pitch of the runner blades.

Return to Top


Click photo to enlarge,
use back button to return to page

Runner hub being placed on cribbing in yard.

Return to Top


Click photo to enlarge,
use back button to return to page

Wicket gate outer trunnion housings fitted with new seals and spherical bearings ready to be reinstalled

Return to Top


Click photo to enlarge,
use back button to return to page

Application of Belzona 1121 Super XL-Metal and 1341 Supermetalglide on cavitated area immediately downstream of runner

Return to Top


Click photo to enlarge,
use back button to return to page

Refurbishing Jewett City mini turbine in Rawson Mfg. shop in Putnam, CT, February 2006. Black lab "Truffel" inserted for scale purposes only.

Return to Top


Click photo to enlarge,
use back button to return to page

Workshop inside powerhouse

Return to Top


Click photo to enlarge,
use back button to return to page

Interfacing for datalogger and PLC programming.

Return to Top


Click photo to enlarge,
use back button to return to page

Allis Chalmers Kaplan turbine

Return to Top


Click photo to enlarge,
use back button to return to page

Siemens synchronous generator

Return to Top


Click photo to enlarge,
use back button to return to page

Mini turbine/generator providing minimum flow requirement

Return to Top


Click photo to enlarge,
use back button to return to page

Disassembly of Jewett City turbine servo piston to replace aged o-rings

Return to Top


Click photo to enlarge,
use back button to return to page

Forebay showing trash racks and trash rake system

Return to Top


Click photo to enlarge,
use back button to return to page

Trash rack support beams were water blasted (250,000 psi), sand blasted, epoxy primer, 3 coats epoxy topcoat.

Return to Top


Click photo to enlarge,
use back button to return to page

New galvanized trash racks being hoisted into place after removal of old corroded racks.

Return to Top


Click photo to enlarge,
use back button to return to page

SHI employee Bob shows newly installed first trash rack panel with access hatch removed.

Return to Top


Click photo to enlarge,
use back button to return to page

New trash racks in position, trash rake is near bottom position, access man hole visible.

Return to Top


Click photo to enlarge,
use back button to return to page

SHI employee Bob services mini unit head gate.

Return to Top


Click photo to enlarge,
use back button to return to page

New galvanized trash racks moving into position assisted by SHI owner Duncan.

Return to Top


Click photo to enlarge,
use back button to return to page

new trash rack/trash rake/conveyor system installed by SHI.

Return to Top


Click photo to enlarge,
use back button to return to page

Blasting and epoxy coating turbine throat ring and wicket gates.

Return to Top


Click photo to enlarge,
use back button to return to page

Switchgear with new Beckwith protective relays.

Return to Top


Click photo to enlarge,
use back button to return to page

Tailrace showing tailgate gantry system.

Return to Top


Click photo to enlarge,
use back button to return to page

Intake showing trash racks.

Return to Top


Click photo to enlarge,
use back button to return to page

SHI designed oil pump/filter system.

Return to Top


Click photo to enlarge,
use back button to return to page

Servo piston which controls blade movement.

Return to Top


Click photo to enlarge,
use back button to return to page

SHI designed regenerative blower system which eliminates seal leakage.

Return to Top


Click photo to enlarge,
use back button to return to page

Bedrock excavation for powerhouse construction circa 1983. Man inserted for scale purposes only.

Return to Top


Click photo to enlarge,
use back button to return to page

Powerhouse construction illustration extensive rebar reinforcement and generator pit.

Return to Top


Click photo to enlarge,
use back button to return to page

Powerhouse construction showing draft tube fabrication.

Return to Top


Click photo to enlarge,
use back button to return to page

Typical engineering drawing showing upstream bearing design.

Return to Top


Click photo to enlarge,
use back button to return to page

Wicket gate hydraulic actuator and control ring.

Return to Top


Click photo to enlarge,
use back button to return to page

Interior of powerhouse looking upstream.

Return to Top


Click photo to enlarge,
use back button to return to page

500+ page logbook contains entries of notes for every maintenance/repair task performed.

Return to Top


Click photo to enlarge,
use back button to return to page

Two 7HP dewatering pumps and control system designed and installed by SHI.

Return to Top


Click photo to enlarge,
use back button to return to page

SHI owner Duncan redesigned switchgear control system and eliminated half of the relays.

Return to Top


Click photo to enlarge,
use back button to return to page

Forebay, five 10-foot X 10-foot head gates, and 333 acre impoundment.

Return to Top

Dayville Pond Hydro >>

HOME | WHAT IS HYDRO | BENEFITS OF HYDRO | THE ROLE OF RENEWABLES | WYRE WYND SITE | DAYVILLE POND SITE | PHOTOS | CONTACT

©Copyright 2014, Summit Hydropower, Inc. All rights reserved.